Achievements For FY 2018-2019
Project name: Kabuga – Kamwenge road 11.6km.
Works done included:
- Bush clearing done to clearance width
- Road shaping to camber and cross fall with a motor grader
- Pothole filing
- Repair of end structures done in missionary work in 1:3 cement sand mix
- Swamp raising
- Spot gravelling and road compaction
- Back sloping 11.6km
- Culvert installation 4lines 900mm diameter.
- Works completed
Project name: Nkoma – Mahani – Kagasha – Biguli road 20.1km
Works done included:
- Re-establishment of road alignment
- Bush clearing done to clearance width 20.1km
- Road shaping to camber and cross fall with a motor grader 20.1km
- Pothole filing
- Spot gravelling
- Repair of end structures
- Back sloping 20.1km
- Works completed
Routine mechanized maintenance works on Kyotamushana – Katooma
Works done included:
- Bush clearing
- Form work timber
- Redecking of the bridge in 1:1:2 reinforced concrete with Y16 at 150mm center to center with lake sand, and crushed stone aggregates.
- Opening of drains ie miter drains catch water drains and side drains.
- Pothole filing
- Raising of the approaches 50m either side
- River training
- Works completed
Routine manual maintenance under road gang system (November/December on the following roads
- Kiyagara – Bunoga 10.3km
- Kyakanyemera – Mpanga 9.2km
- Kabujogera – Nyaruhanda 6km
- Kyotamushana – Katooma 14.6km
- Rwentuha – Mahyoro road 23.4km
- Nyabbani – Kinaga – Kicwamba 14.2km
- Kamwenge – Kabuga 11.4km
- Kabuga – Mpanga 13.6km
- Bigodi – Busiriba – Bunoga 16.6km
- Nkoma – Mahani – Kagasha – Biguri road 20km
- Kabingo – Rwensikiza Road 9.6km
- Ruhagura – Kigoto – Bwera 15km
- Ntuntu – Kicheche Road 6.7km
- Kamwenge – Kyabandara – Nkoongoro Road 19.4km
- Ruhiga – Kamilla 13.6km
- Kahunge – Nkarakara – Kiziba 13.2km
Total Length District Roads 226.5km
Works done included:
- Re-establishment of road alignment
- Inspection of road section daily to remove obstructions
- Bush clearing
- Pothole filling
- Culvert cleaning
- Side miter drains opening
- Gravel patching
Routine manual maintenance under road gang system 62,326,000/= (April and May 2017)Routine mechanized maintenance of Bigodi – Busiriba – Bunoga road 16.6km a
Works done included:
- Re –establishment of the road alignment.
- Bush clearing to clearance width 16.6km
- Road shaping to camber and cross fall 16.6km
- RE opening of drains ie miter drains catch water drains and side drains.
- Pothole filing
- Culvert cleaning
- Back sloping 15.4km
Project Name: Construction of 3-class room block, 2-class room block and 5-stance VIP lined latrine and supply of furniture at Kamwenge primary school
Works done include,
- Bush clearing to clearance width
- Trench excavation
- Laying of hard core
- Site concrete
- Walling
- Roofing
Works completed and handed over for use.
Project Name: Completion of Rukunyu General ward
- Works done include,
- Bush clearing to clearance width
- Trench excavation
- Laying of hard core
- Site concrete
- Works are ongoing at 25% complete
Project Name: Construction of 2-class rooms, supply of furniture 2no 5-stance latrine at Mirembe K Primary school under SFG
- Works done include,
- Bush clearing to clearance width
- Trench excavation
- Laying of hard core
- Site concrete
- Walling
- Roofing
- Works completed and handed over.
Project Name: Construction of 2-class rooms and office and supply of furniture ST Paul primary school .
- Works done include,
- Bush clearing to clearance width
- Trench excavation
- Laying of hard core
- Site concrete
- Walling
- Works completed and handed over.
Project Name: Partial Completion of the District administration Block
Works include
- Plumbing works
- Electrical installation
- Ceiling finishes
- Fixing of guard rails
- Fixing external and internal doors
- Painting of walls and ceiling finishes
- Floor finishes in terrazo
Project Name: Completion of Construction of a water borne toilet at Rukunyu Hospital
Works are ongoing at 95% complete
Construction of 5-stance lined latrine at a cost of 49,708,680/=
- Mugobwa primary school
- Iryangabi Primary school
- Kicheche primary Schoo
- Renovation of Kicheche Subcounty staff quarters.
- Construction of Staff quarters at Mbongera health center II in Kamwenge Sub County.
- Partial Completion of Busiriba Subcounty Head quarters
- Partial completion of Kamwenge Subcounty head quarters in Nyabitusi parish.
Batch CAIIP-3 Roads/projects include
- Supervision of the construction of an Agro Processing Facility in Mahyoro Kyendangara Market. drying platform, 5-stance pitlined latrine and installation water tank.
- Works are complete.
- Works on going
- Repaired the tipper lorry No Lg 0005-044 ie Replaced self starter and distributer box
- Repaired the grader ie break system, self starter, Tandem chain, Hydraulic horse pipe, circle drive system and general service .
- Repaired the department vehicle No Lg 0072-47 .
- The district is still continuously faced with the problem of lack of a professional prequalified contractor for both motor vehicles and motorcycles which has also contributed to the delays in the maintenance process.
- Slow response to calls for quotations by the only one service provider on the side of repair and maintenance of motor vehicles and several complaints about his shoddy work also frustrate the process.